Candleriggs Square – Glasgow

BTR Developments
Project Specification:
OUR CLIENT : AEM Limited
MAIN CONTRACTOR : Graham Group
LOCATION : Glasgow
PROJECT SIZE : 346 Residential Units
Design & Install Criteria:
  • BS9251:2014
  • Cat 3
  • Shared water supplies
  • 27 ICVs split up throughout over two risers
  • 2446 sprinkler heads
  • BS9990:2015
  • Wet riser system Block A Level 0 – Level 16
  • 45,000 litre split storage tank
  • Twin diesel pump set
  • BS9990:2015
  • Dry Riser System
  • Block B Level 0 – Level 10
  • Block C Level 0 – Level 10
Key Details

Build-to-Rent (BTR) Scheme: GRAHAM Construction developed the £81.5 million BTR project, which includes 346 residential units and a small car park. The building features a mix of studio, one-, two-, and three-bedroom apartments, including six duplex penthouses.
Amenities: The development includes communal dining spaces, a gym, a business lounge, and a games room.

“The project was a challenge from the start due to the limited time we had to supply the full design and start the onsite install. However once we got going it became a good contract to be involved in and one that we are proud to have delivered excellent Active fire protection systems.

James Bryceland